SIARAN MEDIA/MEDIA RELEASE

KEMENTERIAN KEWANGAN MALAYSIA
MINISTRY OF FINANCE MALAYSIA


The Final Cost Of The East Coast Rail Link (ECRL) Project Is Actually RM81 Billion And Must Be Reduced Significantly To Make It Viable Financially


 

The final cost of the East Coast Rail Link (ECRL) project is actually RM81 billion and must be reduced significantly to make it viable financially. The ECRL project is also not expected to cover its operating costs. Indeed the RM81 billion project cost does not include operating deficit, which cannot be determined for now. Furthermore, the Selangor state government objects strongly to the completion of Gombak-Port Klang portion of the rail line.

To recap, the ECRL project was first approved by the Cabinet on 21 October 2016 while the Engineering, Procurement, Construction and Commissioning Agreement was signed with China Communication Construction Company (CCCC) on 1 November 2016. The original project scope was to build a rail line from the Integrated Transport Terminal (ITT) Gombak in Selangor to Wakaf Bharu in Kelantan at a cost of RM46 billion.

On 13 May 2017, the previous administration signed an additional agreement with CCCC to carry out Phase 2 of the project, which was to extend the line from ITT Gombak to Port Klang for RM9 billion. Earlier on 3 May 2017, the Cabinet approved the northern extension of the project from Wakaf Bharu to Pengkalan Kubor in Kelantan, for the value of RM1.28 billion. Subsequently on 23 August 2017, the Cabinet further approved the upgrading of the ECRL to a double-tracking project which would cost an additional RM10.5 billion.

Based on these figures, the basic cost of construction of the 688.3km rail line amounts to RM66.78 billion. The breakdown of the RM66.78 billion is provided in Table 1.

Table 1: Construction Cost Breakdown

Phase Scope Cost (RM mil)
Phase 1 ITT Gombak-Wakaf Bharu 46,000
Phase 2 ITT Gombak-Port Klang 9,000
Enhancement

Double tracking

10,500

Extension line: Wakaf Bharu-
Pengkalan Kubor

1,280
 Total  66,780


However, the total cost of ECRL will be RM80.92 billion after taking into account land acquisition, interest, fees and other operational costs. This is reflected in Table 2 below.


Table 2: Total Cost of ECRL

Component Cost (RM mil) Total cost (RM mil)
Development Cost   69,830
Construction Cost 66,780  
Land Acquisition Cost 2,500  
Working Capital 50  
Other Operational Cost 500  
Financing Cost   11,090
Interest 7,444  
Sukuk Coupon 3,192  
Commitment Fee 238  
Management Fee 216  
Total   80,920


To date, the Government of Malaysia, via its wholly-owned operating subsidiary, Malaysia Rail Link Sdn Bhd (MRL), has paid CCCC the sum of RM19.68 billion, comprising of (i) advance payment of RM10.02 billion and (ii) progress payment of RM9.67 billion. *rounding estimation

The advance payment of RM10.02 billion however, is backed by an advance payment bond of the equivalent amount. This advance payment bond may be redeemed by MRL to recover up to RM10.02 billion. In other words, in the event of a worst case scenario, the Federal Government can recover RM10.02 billion of the RM19.68 billion paid.

Based on the above facts and figures, as well as the feasibility studies of the project, we expect that the ECRL project will only become financially and economically feasible if there is a drastic price reduction of the project by the CCCC. Discussions on cost will be held with the contracting parties and others involved in the project.

The Federal Government also takes cognisance of the strong objection by the Selangor state government towards the ECRL project, especially with respect to the rail link from ITT Gombak to Port Klang. Section 20A of the Town and Country Planning Act 1976 states that Federal Government needs to consult the state government before carrying out any federal project in the relevant state.

The Selangor state government’s objection is principally based on Selangor’s application to establish the 16km-long Klang Gates Quartz Ridge, which is the longest of its kind in the world, as a UNESCO World Heritage Site. Completing the Gombak-Port Klang link would guarantee the failure of Selangor’s application.

Only after a significant price reduction on the ECRL is obtained, will the Federal Government enter into discussions with the Selangor state government on the merits of the ECRL project as compared to the possible UNESCO World Heritage Site listing.


Sayangi Malaysiaku!

Lim Guan Eng
Minister of Finance
Putrajaya
3 July 2018


Download attachments: